The Downtown Escondido Makeover Continues: Grand Avenue

Construction updates

Major Milestone: Final Phase Begins! 
We're excited to announce the start of Subphase 3, this marks the final stage of the Grand Avenue Vision Project Phase II. With this milestone, we're on track for full project completion in Spring 2025.

This Week's Progress:

  • Landscaping teams will begin planting trees along Subphase 1
  • Installation of decorative fencing continues in completed areas
  • Kalmia traffic circle now open, restoring access between Juniper and Kalmia

Traffic Alerts: Motorists should be aware that the Broadway and Grand intersection is now closed as part of Subphase 3 construction. Please use Valley Parkway or 2nd Avenue as detour routes and plan for extra travel time. The Broadway intersection will also be closed to pedestrian traffic. Please be aware of all signage and remain on the designated pedestrian walkways. While we're pleased to announce the Kalmia traffic circle is now open and restoring access between Juniper and Kalmia, please note that the section from Kalmia to Maple will remain closed until project completion. Watch for temporary signage in all affected areas.

Looking Ahead: Our teams will continue focusing on beautification elements in completed sections while pushing forward with final construction work. We remain on schedule for the Spring 2025 completion. Thank you for your continued interest in the Grand Avenue Vision Project. Your patience during construction helps us create a more vibrant downtown for everyone to enjoy.

Construction along Grand Avenue: New traffic circle

A sweet adventure awaits! 

Another section of Grand Avenue has been completed! Don’t miss the chance to check out the recent improvements and cruise through the new traffic circle. While you're here, take a moment to support local businesses along the way and experience all the vibrant changes this area has to offer!

Attention all chocolate lovers! The Downtown Business Association's Chocolate Festival is right around the corner! Join us on Saturday, February 15 for a day of chocolate tasting and fun exploring downtown Escondido. Get your tickets now on their website and get ready for a memorable, mouthwatering adventure!

Construction Details

The Grand Avenue Vision Project is all about preserving Escondido’s historic small-town look and feel while infusing new energy and vibrancy into the heart of Escondido. This exciting initiative aims to transform Grand Avenue into a welcoming and pedestrian-friendly corridor and boost the economic vitality of our downtown area. 

Construction Hours and Details 

Construction will take place Monday through Friday from 6:00 a.m. to 2:30 p.m. During the construction of Phase II, Grand Avenue will be closed to through traffic. However, pedestrian access will remain open to all businesses.  

Free parking is available throughout the duration of the project and can be found using the interactive parking map. Please be sure to observe all traffic control signs and do not move traffic cones or barriers. To help protect public safety, please remain on the designated pedestrian walkways.

Questions and Project Information 

Have any questions or comments? We have created several resources that will be updated regularly to ensure construction impacts are readily accessible.

  • City’s website: https://www.escondido.gov/300/Grand-Avenue-Vision-Project
  • Project hotline: 760-839-4822 
  • Project email: grandavenueproject@escondido.gov  